The building site at Onesua College
I learnt something new today the hole is
to be 50cm deep and 40 cm wide a calibrated tool
dug by hand the digger broke down ( always happens)
The first 15 cubic meters of washed sand delivered
with another 35 cubic meters to come
and 90 cubic meters coral to come
The Rebar being positioned to drop in the hole soon
Day 1 with the men for the surrounding community villages
working in teams one building 1 village