The building site at Onesua College 
I learnt something new today the hole is 
to be 50cm deep and 40 cm wide a calibrated tool
dug by hand the digger broke down ( always happens)




The first 15 cubic meters of washed sand delivered 
with another 35 cubic meters to come 
and 90 cubic meters coral to come


The Rebar being positioned to drop in the hole soon


 Day 1 with the men for the surrounding community villages
working in teams one building 1 village 